At the beginning of a project, the project manager holds a risk workshop with the project team and the key customer stakeholders. After the workshop, they produce a matrix with several risks. Their probabilities, and impacts for the project. What type of risk analysis was performed in the workshop?
A、Qualitative risk analysis
B、Quantitative risk analysis
C、Categorization risk analysis
D、Delphi technique risk analysis