Weather conditions are identified as critical risks for an offshore wind park development project. To mitigate risks associated with bad weather conditions, the project manager creates a contingency plan to and more time to the planned schedule. At the time of execution a hurricane comes close to the wind park area so that all activities need to be stopped immediately.What should the project manager next?
A、Update the risk register and create a change request.
B、Get additional approval from the steering committee.
C、Change the schedule of the team members accordingly
D、Avoid any chances to keen the project management plan as if was approved.